Project Summary: Line Removal & Repainting Scope
At the client's request, we were brought in to completely black out all existing striping, including old lane lines and selected Chevron areas, in preparation for new layout painting. Due to the extent of previous markings and the surface type, the job required:
Full surface coverage using black-out paint to fully conceal former lines and Chevrons
Surface cleaning and prep time before reapplication to ensure adhesion and durability
Multiple drying phases between blackout and repainting stages
Accurate re-striping and layout work for high-visibility traffic markings, aligned with the new design
The project spanned two full days to ensure proper curing between blackout and repainting phases, compliance with spec requirements, and professional finish quality.
Perimeter Lines after being Blacked out and restripedÂ
Before
After
After
Chevrons after being Blacked out and restripedÂ
Before
After
Before
After
Blacked out and restriped double lines between Lane 1 & Lane2